Scope break
Also called extra work, out of scope, T&M extra.
A scope break is the moment the work left the base contract. The extra still has to be captured with the same discipline as the bid — classes, hours, and a rate — or it dies in a meeting.
Why a note in the daily is not enough
“Helped the plumber, 3 hours” does not survive billing. The LEM needs the extra named, the people and iron on that extra, and the rate sheet that applies. SubTrack tracks scope breaks natively so the extra is not buried in the base ticket.
When it becomes a change order
Once the extra is defined and priced, many jobs convert T&M tickets into a change order. The tickets are the backup. If they are sloppy, the CO is sloppy.
Scope break FAQ
Is a scope break the same as a change order?
A scope break is the field event. A change order is the commercial wrap. T&M tickets often become the backup for the CO.
Who decides it is extra?
The contract and the people who signed it. The ticket should still record the hours so the argument has facts.
The index is a benchmark. Rate sheets are how you bill.
Rates shows public charge-out ranges. SubTrack rate sheets lock your crew numbers into a template the field actually bills from, on every LEM.
One template, every job
Labor, equipment, materials, and subs live in one sheet. Assign it to a project and tickets read the same numbers.
OT and markup apply themselves
Standby, overtime, and markup rules ride with the sheet. The field does not retype them.
The client sees what they signed
Line items match the agreed rates. Fewer disputes, faster approvals.
Project rate sheet
Labor · assigned to the job
| Position | Reg. rate | OT rate |
|---|---|---|
| Foreman | $72/hr | $108/hr |
| Operator | $68/hr | $102/hr |
| Laborer | $35/hr | $52.50/hr |