Construction glossary

Swell and shrink

Also called bank versus loose, load factor, shrink factor.

Dirt changes volume when you dig it and when you compact it. Swell is bank to loose. Shrink is bank to compacted. If you count trucks on bank cubic metres, you will be short.

Typical factors (confirm on site)

DIRT’s defaults match common field books: sand/gravel about 12% swell, common earth about 25%, clay about 30%, blasted rock about 50%. Shrink on placement is a different number — common earth often around 12%. These are starting points, not a soils report.

The conversion

Loose = bank × (1 + swell). Compacted = bank × (1 − shrink). Load factor is 1 / (1 + swell). A 100 m³ bank cut of common earth is about 125 m³ loose in the truck. Run the swell calculator before you size the haul.

Swell and shrink FAQ

Is trench volume in DIRT bank or loose?

Bank, from the dimensions you type. Apply swell before you count trucks.

What is load factor?

Bank volume per unit of loose volume: 1 / (1 + swell). A 25% swell is a 0.80 load factor.

Rate sheets

The index is a benchmark. Rate sheets are how you bill.

Rates shows public charge-out ranges. SubTrack rate sheets lock your crew numbers into a template the field actually bills from, on every LEM.

One template, every job

Labor, equipment, materials, and subs live in one sheet. Assign it to a project and tickets read the same numbers.

OT and markup apply themselves

Standby, overtime, and markup rules ride with the sheet. The field does not retype them.

The client sees what they signed

Line items match the agreed rates. Fewer disputes, faster approvals.

Project rate sheet

Labor · assigned to the job

PositionReg. rateOT rate
Foreman$72/hr$108/hr
Operator$68/hr$102/hr
Laborer$35/hr$52.50/hr