Aggregate tonnage calculator

Turn a pad, road base, or trench backfill into tonnes. Volume times placed density is the order you send to the pit, not the loose pile on the truck.

Formula

Volume = length × width × depth. Tonnes = volume × density (t/m³). Short tons = tonnes × 1.102. Use compacted density for placed base, loose density for a stockpile.

Worked example

A 60 m × 4 m lane, 150 mm of compacted road crush at 2.24 t/m³ is 36 m³ and about 81 tonnes. Order a little extra for waste and the last truck.

Length and width in m or ft, depth in mm or inches, density in t/m³ or lb/yd³. Presets for crush, clear stone, sand, pit-run, rip-rap, and millings.

Open the calculator

Field calculators

Estimates for bidding and the truck. Confirm against survey, geotech, and scale tickets before you price.

Aggregate & gravel tonnage

Tonnes of gravel to place and compact over an area: road base, pad, driveway, or bedding lift.

Material

Length

m

Width

m

Compacted depth

m

Placed density

t/m³

Waste / over-run

%

Truck payload

t

Order quantity

290.3t

Truck loads

20.74

Aggregate tonnage calculator FAQ

Do I use loose or compacted density?

Compacted for material you are placing to grade. Loose for a pile you are loading out. Mixing them under-orders or over-orders the pit.

How many trucks is that?

Divide tonnes by the legal payload, not the box volume, for dense crush. Then use the haul calculator for cycle time.

Can I use this for concrete?

It will give a mass from a volume and a density. Concrete is usually ordered in cubic metres or yards, not tonnes. Use the excavation tab for a slab volume.

How does this become a ticket?

DIRT sizes the tonnes. SubTrack records the trucks, loader, and labor against the project rate sheet on the LEM.

The math is free. The ticket still has to get paid.

DIRT sizes the work. SubTrack turns the labor, iron, and material on the job into a signed LEM against your rate sheet.