Going digital only pays if the ticket still gets signed and billed. These seven practices separate a collectible T&M ticket from a disputed one, whether you use SubTrack or not.

Last updated: November 4, 2026

  1. Agree the rate sheet before the extra starts

    Load the contracted labor, equipment, material, and subcontractor rates on the project before anyone writes a ticket. A ticket priced from an agreed sheet is hard to argue with. A ticket priced after the fact invites a dispute. Public charge-out benchmarks can sanity-check a class, but your contract governs.

  2. Write the ticket the same day

    Crews remember hours, equipment, and quantities on the day. A week later the ticket becomes a reconstruction, and reconstructions get cut. Make same-day tickets the rule.

  3. Separate extra work from base scope

    Mark which lines are extra work, force account, or a scope break, so the client signs for exactly what changed. A ticket that mixes base and extra work is easy to reject as a whole.

  4. Capture proof while you are there

    Note the condition or instruction that caused the extra, who gave it, and when. Photos and receipts that explain why the work happened make the ticket easier to approve and harder to dispute later.

  5. Get the signature before the crew leaves

    The best time for client approval is while the client can still see the work. A secure link the client opens on a phone, with no account to create, removes the reason to wait.

  6. Fix revisions on the ticket, not in email

    When a ticket comes back, change it and resend it so the history stays with the record. Email threads lose track of which version the client actually approved.

  7. Bill from the approved record

    Build the invoice from approved tickets only, and attach them. When the field record and the invoice match line for line, there is less left to dispute.

FAQ

What is the most important T&M best practice?

Agree the rates before the work starts and get the ticket signed the same day. Together they remove the two easiest reasons for a client to push back: a rate they never agreed to and work they did not see.

Do these practices need software?

No. They work on paper too. Software makes them easier to keep: rates fill in from the rate sheet, the client signs from a link, and revisions stay on the ticket.

Start your first daily ticket today.

Run SubTrack on a live job before you pay for a seat. If it does not save your crew time, you walk away.

  • Free to try on any project
  • No credit card required
  • Setup help included

We're a young company and we build with our customers. Tell us what your crew needs: we read every suggestion and work with you on it. See what's coming on our roadmap.

Comparing costs? See pricing or Calculate ROI.

What happens next

  1. Create your account

    Sign up in a few minutes. No sales call needed.

  2. Add your crew and rates

    Enter them yourself, or send us your roster and rate sheets and we load them for you.

  3. Log the first daily ticket

    A supervisor can log the first ticket from the field the same day.