How do purchase orders and AFE numbers work with T&M tickets?

The client issues a PO or AFE number that authorizes the spend. Every T&M or LEM ticket for that work carries the number, and the invoice quotes it. Tickets without the right number are the ones accounts payable sends back.

Last updated: November 25, 2026

PO, AFE, and change order: what each one does

A purchase order (PO) is the client's commitment to pay for defined work or materials, usually up to a set amount. An AFE (authorization for expenditure) is a budget approval, common with oil and gas operators, that the client uses to charge the cost to the right project. A change order changes the contract scope or price. The T&M or LEM ticket is the record of the work done under any of them.

Get the number before the work starts

Ask for the PO or AFE number when the extra is agreed, not when the invoice is due. If the client says to start now with the PO to follow, get that instruction in writing and note it on the ticket. Add the number to every ticket as soon as it arrives, before any ticket is invoiced.

One PO, many tickets

A single PO often covers many daily tickets. Track the total of signed tickets against the PO value every day. When the next ticket will take you past the PO value, tell the client and ask for a revised PO or a new one before the crew does the work.

A worked example

These numbers are made up for illustration. The client issues a PO for $25,000 of T&M extras. Over a week the crew writes five signed daily tickets: $4,200, $5,150, $3,980, $6,400, and $4,870. That is $24,600, leaving $400 on the PO. Tomorrow's work will pass the PO value, so the PM asks for a revised PO today instead of finding out when the invoice is rejected.

Why invoices with a PO get sent back

The usual reasons are a missing or wrong PO or AFE number, an invoice that goes over the PO value, a PO or AFE the client has already closed, and one invoice that mixes tickets from two POs. Each one is easier to catch on the ticket than in the client's accounts payable queue.

Where SubTrack fits today

In SubTrack, clients and contractors can add a PO or AFE number to a LEM, so the number stays with the ticket the client signed. SubTrack is not purchase order software. It does not issue POs, track PO budgets or remaining balances, or match POs to supplier invoices. Keep the PO value and balance in your accounting or purchasing system, and use the PO or AFE number on each LEM to pull the right tickets for each invoice.

FAQ

Does every T&M ticket need a PO number?

When the client works with purchase orders, yes. Put the PO or AFE number on every ticket for that work, so the invoice and every ticket behind it point to the same authorization.

What is an AFE number?

AFE stands for authorization for expenditure. It is a budget approval number, common with oil and gas operators, that tells the client's accounting where to charge the cost.

What happens when T&M work goes past the PO value?

Work past the PO value without a revised PO is at risk of not being paid. Track signed tickets against the PO and ask for a revision before you reach it.

Does SubTrack manage purchase orders?

No. Clients and contractors can add a PO or AFE number to a LEM in SubTrack, but SubTrack does not issue POs, track PO budgets or balances, or match POs to supplier invoices.

Start your first daily ticket today.

Run SubTrack on a live job before you pay for a seat. If it does not save your crew time, you walk away.

  • Free to try on any project
  • No credit card required
  • Setup help included

We're a young company and we build with our customers. Tell us what your crew needs: we read every suggestion and work with you on it. See what's coming on our roadmap.

Comparing costs? See pricing or Calculate ROI.

What happens next

  1. Create your account

    Sign up in a few minutes. No sales call needed.

  2. Add your crew and rates

    Enter them yourself, or send us your roster and rate sheets and we load them for you.

  3. Log the first daily ticket

    A supervisor can log the first ticket from the field the same day.