Labor

Skilled laborer / pipelayer charge-out rates

Skilled laborer / pipelayer charge-out is grade checking, pipe laying, and trench work. It is not a general laborer. Lock the class on the sheet so the ticket does not collapse the two lines.

Each row is one region. Currency is CAD or USD as labeled on the row. Open a region page for the rest of the book.

Skilled laborer / pipelayer by region

RegionLowCentralHigh
Alabama

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Alabama

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
Alaska

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Alaska

Operator not stated. Fuel not stated.

$85 USD

$95 USD

$105 USD
Alberta

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Alberta

Operator not stated. Fuel not stated.

$70 CAD

$80 CAD

$95 CAD
Arizona

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Arizona

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$75 USD
Arkansas

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Arkansas

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
British Columbia

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · British Columbia

Operator not stated. Fuel not stated.

$75 CAD

$90 CAD

$100 CAD
California

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · California

Operator not stated. Fuel not stated.

$75 USD

$85 USD

$95 USD
Colorado

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Colorado

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$80 USD
Connecticut

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Connecticut

Operator not stated. Fuel not stated.

$75 USD

$85 USD

$90 USD
Delaware

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Delaware

Operator not stated. Fuel not stated.

$65 USD

$75 USD

$80 USD
Florida

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Florida

Operator not stated. Fuel not stated.

$55 USD

$60 USD

$70 USD
Georgia

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Georgia

Operator not stated. Fuel not stated.

$55 USD

$60 USD

$70 USD
Hawaii

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Hawaii

Operator not stated. Fuel not stated.

$90 USD

$105 USD

$110 USD
Idaho

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Idaho

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Illinois

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Illinois

Operator not stated. Fuel not stated.

$65 USD

$75 USD

$85 USD
Indiana

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Indiana

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Iowa

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Iowa

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Kansas

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Kansas

Operator not stated. Fuel not stated.

$55 USD

$60 USD

$65 USD
Kentucky

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Kentucky

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
Louisiana

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Louisiana

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
Maine

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Maine

Operator not stated. Fuel not stated.

$65 USD

$75 USD

$80 USD
Manitoba

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Manitoba

Operator not stated. Fuel not stated.

$65 CAD

$75 CAD

$85 CAD
Maryland

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Maryland

Operator not stated. Fuel not stated.

$70 USD

$80 USD

$85 USD
Massachusetts

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Massachusetts

Operator not stated. Fuel not stated.

$75 USD

$90 USD

$95 USD
Michigan

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Michigan

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Minnesota

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Minnesota

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$75 USD
Mississippi

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Mississippi

Operator not stated. Fuel not stated.

$50 USD

$55 USD

$60 USD
Missouri

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Missouri

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Montana

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Montana

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Nebraska

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Nebraska

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Nevada

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Nevada

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$80 USD
New Brunswick

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · New Brunswick

Operator not stated. Fuel not stated.

$65 CAD

$75 CAD

$85 CAD
New Hampshire

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · New Hampshire

Operator not stated. Fuel not stated.

$65 USD

$75 USD

$80 USD
New Jersey

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · New Jersey

Operator not stated. Fuel not stated.

$75 USD

$85 USD

$95 USD
New Mexico

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · New Mexico

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
New York

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · New York

Operator not stated. Fuel not stated.

$75 USD

$90 USD

$100 USD
Newfoundland & Labrador

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Newfoundland & Labrador

Operator not stated. Fuel not stated.

$70 CAD

$80 CAD

$90 CAD
North Carolina

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · North Carolina

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$70 USD
North Dakota

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · North Dakota

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Northern Canada (YT/NT/NU)

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Northern Canada (YT/NT/NU)

Operator not stated. Fuel not stated.

$90 CAD

$100 CAD

$115 CAD
Nova Scotia

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Nova Scotia

Operator not stated. Fuel not stated.

$65 CAD

$75 CAD

$85 CAD
Ohio

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Ohio

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$75 USD
Oklahoma

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Oklahoma

Operator not stated. Fuel not stated.

$55 USD

$60 USD

$65 USD
Ontario

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Ontario

Operator not stated. Fuel not stated.

$75 CAD

$90 CAD

$100 CAD
Oregon

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Oregon

Operator not stated. Fuel not stated.

$65 USD

$80 USD

$85 USD
Pennsylvania

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Pennsylvania

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$80 USD
Quebec

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Quebec

Operator not stated. Fuel not stated.

$70 CAD

$80 CAD

$95 CAD
Rhode Island

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Rhode Island

Operator not stated. Fuel not stated.

$70 USD

$80 USD

$85 USD
Saskatchewan

Grade checking, pipe laying, trench work.

Labor charge-out · CAD/hr · Reference estimate · effective 2026-08 · Saskatchewan

Operator not stated. Fuel not stated.

$70 CAD

$80 CAD

$90 CAD
South Carolina

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · South Carolina

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
South Dakota

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · South Dakota

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Tennessee

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Tennessee

Operator not stated. Fuel not stated.

$55 USD

$60 USD

$65 USD
Texas

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Texas

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$75 USD
Utah

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Utah

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$75 USD
Vermont

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Vermont

Operator not stated. Fuel not stated.

$65 USD

$75 USD

$80 USD
Virginia

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Virginia

Operator not stated. Fuel not stated.

$60 USD

$70 USD

$75 USD
Washington

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Reference estimate · effective 2026-08 · Washington

Operator not stated. Fuel not stated.

$70 USD

$80 USD

$90 USD
West Virginia

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · West Virginia

Operator not stated. Fuel not stated.

$50 USD

$60 USD

$65 USD
Wisconsin

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Wisconsin

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD
Wyoming

Grade checking, pipe laying, trench work.

Labor charge-out · USD/hr · Modeled benchmark · effective 2026-08 · Wyoming

Operator not stated. Fuel not stated.

$55 USD

$65 USD

$70 USD

Use your agreed rates on every daily ticket.

These public ranges are a benchmark. SubTrack stores the rates you agreed with the client on a project rate sheet. Crews apply those rates to labor, equipment, materials, and subcontractors on the daily ticket. The same figures carry into reporting and the billing documents you send.

Skilled laborer / pipelayer rates FAQ

What is a typical skilled laborer / pipelayer charge-out rate?

Skilled laborer / pipelayer charge-out is grade checking, pipe laying, and trench work. It is not a general laborer. Lock the class on the sheet so the ticket does not collapse the two lines. Open a region page for the local number, or a region plus skilled laborer / pipelayer page for a single market.

Is the skilled laborer / pipelayer figure a wage or a charge-out?

A labor charge-out, not a wage. Burden, overhead, and margin are already in the published range. Overtime rules belong on the project rate sheet.

Can I bill the central skilled laborer / pipelayer reference?

Not from this page alone. The central value is a public check, not a measured market median. SubTrack rate sheets are where your class, standby, and OT actually live.