Your privacy choices

We use necessary storage for site preferences. Analytics and advertising tools stay off until you allow them.

USA · USD

Arkansas charge-out rates

Also called AR, Little Rock and Northwest Arkansas. Rates by SubTrack.

Arkansas rates follow Little Rock civil, river industrial, and Northwest Arkansas commercial. The book is tighter than Texas Gulf Coast work. These USD figures are fully loaded T&M charge-out ranges, not take-home pay.

Prices in USD. Fully loaded T&M charge-out, not wages.

Arkansas labor

TradeUnitLowMedianHigh
Boilermaker

Pressure vessel and boiler work.

/hr$75

$85

$100
Carpenter (Journeyman)

Formwork, framing, finishing.

/hr$60

$65

$75
Concrete Finisher

Placing and finishing structural and flatwork concrete.

/hr$60

$65

$75
Crane Operator (Journeyman)

Mobile and tower crane operation.

/hr$75

$85

$100
Electrician (Journeyman)

Industrial and commercial electrical installation.

/hr$70

$85

$90
General Laborer

Site labor, flagging, general cleanup and support work.

/hr$40

$50

$60
Heavy Equipment Operator

Operator billed separately from bare equipment rate.

/hr$60

$75

$85
HVAC / Refrigeration Mechanic

HVAC installation and service.

/hr$70

$85

$90
Instrumentation Technician

Instrumentation and controls, industrial plants.

/hr$80

$90

$100
Insulator (Mechanical)

Mechanical insulation, industrial settings.

/hr$60

$75

$85
Ironworker

Structural steel erection, rebar placing.

/hr$65

$75

$85
Millwright

Mechanical equipment installation and alignment.

/hr$75

$85

$95
Painter / Coatings (Industrial)

Industrial coatings and blasting.

/hr$60

$65

$80
Pipefitter / Steamfitter

Process and utility piping, industrial settings.

/hr$75

$85

$95
Plumber (Journeyman)

Commercial and industrial plumbing.

/hr$65

$75

$85
Project Manager

Typically billed on T&M for owner-directed extras.

/hr$95

$110

$125
Safety Officer (NCSO/CHST)

Dedicated site safety supervision.

/hr$60

$75

$85
Scaffolder

Scaffold erection and dismantle.

/hr$60

$65

$80
Skilled Laborer / Pipelayer

Grade checking, pipe laying, trench work.

/hr$50

$60

$65
Superintendent

Site supervision above foreman level.

/hr$90

$105

$115
Survey Crew (2-person, equipped)

Two-person survey crew including instruments.

/hr$110

$125

$145
Truck Driver (Class 1 / CDL-A)

Driver billed separately from bare truck rate.

/hr$50

$60

$65
Welder (B-Pressure)

Pressure welding; rate typically excludes rig.

/hr$85

$95

$110
Welder with Rig Truck

B-pressure welder including welding rig truck.

/hr$110

$125

$140
Working Foreman

Trade foreman, typically working with tools.

/hr$75

$85

$95

Arkansas equipment

EquipmentUnitLowMedianHigh
Air Compressor - 185 CFM

Daily bare rental, fuel extra.

/day$80

$100

$120
Articulated Rock Truck - 40 Ton

Bare rate; add operator.

/hr$140

$160

$185
Backhoe - Loader/Backhoe

Bare rate; add operator.

/hr$75

$85

$100
Boom Lift - 60 ft

Bare rate.

/hr$60

$75

$85
Dozer - D6 Class

Bare rate; add operator.

/hr$140

$160

$185
Dozer - D8 Class

Bare rate; add operator.

/hr$195

$220

$250
Excavator - 20 Ton Class (e.g. 320/200)

Bare rate; add operator. Tracked hydraulic excavator.

/hr$130

$145

$170
Excavator - 30 Ton Class (e.g. 330/300)

Bare rate; add operator.

/hr$160

$185

$205
Excavator - 45 Ton Class

Bare rate; add operator. Mass excavation class.

/hr$200

$240

$270
Generator - 100 kW

Daily bare rental, fuel extra.

/day$195

$240

$280
Hydrovac Truck (2-person crew)

Operated rate - includes crew.

/hr$265

$305

$340
Light Tower

Daily bare rental, fuel extra.

/day$95

$125

$150
Mini Excavator - 3-5 Ton

Bare rate; add operator.

/hr$60

$75

$85
Mobile Crane - 100 Ton (operated)

Operated and maintained rate.

/hr$270

$310

$355
Mobile Crane - 60 Ton (operated)

Operated and maintained rate.

/hr$205

$240

$275
Motor Grader - 140/14 Class

Bare rate; add operator.

/hr$135

$155

$175
Motor Scraper - 621/623 Class

Bare rate; add operator.

/hr$190

$215

$245
Packer - Padfoot/Smooth 84"

Bare rate; add operator.

/hr$90

$110

$125
Picker / Boom Truck - 45 Ton (operated)

Operated rate.

/hr$175

$200

$235
Scissor Lift - 26 ft

Daily bare rental.

/day$150

$185

$215
Site Office Trailer

Daily rate, delivery extra.

/day$35

$50

$65
Skid Steer

Bare rate; add operator.

/hr$50

$65

$75
Tandem Gravel Truck (with driver)

Operated rate - driver included.

/hr$100

$120

$135
Telehandler - 10k Class

Bare rate; add operator.

/hr$70

$85

$95
Tractor & End Dump (with driver)

Operated rate - driver included.

/hr$125

$140

$160
Tractor & Lowboy (with driver)

Operated rate - driver included. Equipment moves.

/hr$140

$165

$195
Trencher - Ride-on

Bare rate; add operator.

/hr$80

$90

$110
Water Truck (with driver)

Operated rate - driver included.

/hr$90

$110

$130
Wheel Loader - 3-4 yd Class

Bare rate; add operator.

/hr$115

$135

$150

Arkansas rates FAQ

What are construction charge-out rates in Arkansas?

Arkansas charge-out rates in this index are fully loaded T&M ranges for labor and equipment, in USD, as of 2026-08. They are not wages. Arkansas rates follow Little Rock civil, river industrial, and Northwest Arkansas commercial. The book is tighter than Texas Gulf Coast work. These USD figures are fully loaded T&M charge-out ranges, not take-home pay.

Are Arkansas rates wages or billable T&M?

Billable T&M. Low, median, and high already include a public view of burden, overhead, and margin. They are not take-home pay and they are not a quote.

Can I put these Arkansas numbers on an invoice?

No. This is a public benchmark. SubTrack rate sheets lock your crew numbers to the project so every LEM bills the rate the client signed.

Is this index union or open shop for Arkansas?

It is a blended public range, not a union package and not a PLA. Confirm against the agreement on the job, then store that number on the project rate sheet.

Rate sheets

The index is a benchmark. Rate sheets are how you bill.

Rates shows public charge-out ranges. SubTrack rate sheets lock your crew numbers into a template the field actually bills from, on every LEM.

One template, every job

Labor, equipment, materials, and subs live in one sheet. Assign it to a project and tickets read the same numbers.

OT and markup apply themselves

Standby, overtime, and markup rules ride with the sheet. The field does not retype them.

The client sees what they signed

Line items match the agreed rates. Fewer disputes, faster approvals.

Project rate sheet

Labor · assigned to the job

PositionReg. rateOT rate
Foreman$72/hr$108/hr
Operator$68/hr$102/hr
Laborer$35/hr$52.50/hr